Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

Road works – Worplesdon Road and Holly Lane, Worplesdon

Road works – Worplesdon Road and Holly Lane, Worplesdon

Please see below information regarding the works on Worplesdon Road and Holly Lane, Worplesdon. Multiway signals will be in place as we carry out drainage improvement works.

There will be multiway signals in place from 11 November for approximately 4 weeks as the work is being carried out in 3 phases.

Phase 1

11 – 17 November

3-way lights manually controlled between 8 am and 5 pm. Holly Lane will be reduced to one lane for safety and material storage

Phase 2

18 November to 01 December

3-way signals will be in place 24 hours a day, manually controlled between the hours of 7 am and 7 pm

Phase 3

01 December – 11 December

The road will be assessed and works updated based on progress made

Please see the attached resident letter and map for the details of our works.

Sometimes our plans must change, often due to bad weather or problems on other works in the same programme which can have a knock-on effect. If anything changes with the details of these works, we will let you know.

You and your residents can also find up to date details of the works on www.surreycc.gov.uk/roadworks

Thank you in advance.

If you have any questions please do not hesitate to contact us on 0300 200 1003 or email works.communication@surreycc.gov.uk